info This step is completed by Montenegrin electricity distribution system
Summary print

Preview & Print

Properties

Steps (21) arrow_drop_up arrow_drop_down
Prepare documents  (3) expand_more expand_less
Obtain urban development and technical requirements  (2) expand_more expand_less
Obtain main architectural project and revision report  (2) expand_more expand_less
Obtain an insurance for investor  (1) expand_more expand_less
Obtain a construction permit  (6) expand_more expand_less
Obtain approval for connection to the electrical network  (2) expand_more expand_less
Obtain a measuring device  (2) expand_more expand_less
Sign a contract on connection to electrical network  (2) expand_more expand_less
Sign a contract with electricity supplier  (1) expand_more expand_less

18
Obtain a measuring device
(last modified: 18/10/2017)

Expected results

Measuring device installed

Requirements

Legal justification

1. Law on energetics
Law on energetics
Article 123
2. The rulebook on measuring electricity
The rulebook on measuring electricity
Article 31