Summary print

Preview & Print

Properties

Steps (11) arrow_drop_up arrow_drop_down
Obtain urban development and technical requirements  (2) expand_more expand_less
Obtain the main architectural project  (2) expand_more expand_less
Obtain approval for connection to the electrical network  (2) expand_more expand_less
Obtain a measuring device  (2) expand_more expand_less
Sign a contract on connection to electrical network  (2) expand_more expand_less
Sign a contract with electricity supplier  (1) expand_more expand_less

5
Apply for approval for connection to the electrical network
(last modified: 03/06/2017)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  20 mn
15 days  -  120 days

Contact details

Entity in charge

Montenegrin Electricity Distribution System

Ulica Ivana Milutinovića br. 12, Podgorica 20000
Tel: +382 20 408 400
Website: www.cedis.me

Expected results

Application submission confirmation Application submission confirmation

Requirements

1. Application for connection to the electrical network
Application for connection to the electrical network (original)
or 01 - Libre deuda de patente
ID Card (Simple copy)
In case of a natural person.
2. LLC's Tax ID number
LLC's Tax ID number (original)
In case of a legal person.
In case a new structure is being built, following documents are required:
1. 01 - Libre deuda de patente
Urban development and technical conditions (2 original )
It has to be accompanied by a map of a detailed urban plan in a digital (CD) and a paper form, with routs of infrastructural networks and roads as well as guidelines and requirements for construction of infrastructure and building facilities.
2.
Revised main architectural project (original)
In case a power supply is needed for a construction site, following documents are needed:
1. 01 - Libre deuda de patente
Construction permit (original)
2.
Main architectural project (original)
3.
Approval for connection to the electrical network (original)
For temporary structures, following documents are needed:
1.
Approval for temporary structure's location (original)
2.
Electricity project (original)
In case a change in supplied power is needed, following documents are needed:
1.
Approval for connection to the electrical network (original)
2.
Proof that all dues have been paid (original)
3. 01 - Libre deuda de patente
Ownership certificate (original)
4.
Electricity project (original)

Time frame

Waiting time in queue: Min.   5mn - Max.  10mn
Attention at counter: Min.   5mn - Max.   10mn
Waiting time until next step: Min.   15 days - Max.   120 days

Legal justification

1. Law on energetics
Law on energetics
Article 176
2. The rulebook on electrictricity system operations
The rulebook on electrictricity system operations
Article 40

Additional information

Note 1: Electricity Company of Montenegro has a toll-free info line 19100 that is available on weekdays from 8:00 to 20:00 o'clock. The line provides all relevant information regarding the steps in obtaining the approval for connection to electrical network.
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License