Karakteristike

Koraci (11) arrow_drop_up arrow_drop_down
Obtain urban development and technical requirements  (2) expand_more expand_less
Obtain the main architectural project  (2) expand_more expand_less
Obtain approval for connection to the electrical network  (2) expand_more expand_less
Obtain a measuring device  (2) expand_more expand_less
Sign a contract on connection to electrical network  (2) expand_more expand_less
Sign a contract with electricity supplier  (1) expand_more expand_less

5
Apply for approval for connection to the electrical network
(Posljednja izmjena: 03/06/2017)

Vremenski okvir ( ver detalles )

Sačekajte sljedeći korak

10 mn  -  20 mn
15 dani  -  120 dani

Kontakt detalji

Nadležna institucija

Crnogorski elektrodistributivni sistem

Podgorica 20000
Tel: +382 20 408 400

Očekivani rezultati

Potvrda o predatom zahtjevu Potvrda o predatom zahtjevu

Zahtjevi

1. Zahtjev za priključenje na elektro mrežu
Zahtjev za priključenje na elektro mrežu (original)
ili 01 - Libre deuda de patente
Lična karta (Obična kopija)
In case of a natural person.
2. Rješenje o registraciji PIB
Rješenje o registraciji PIB (original)
In case of a legal person.
In case a new structure is being built, following documents are required:
1. 01 - Libre deuda de patente
Urbanističko tehnički uslovi (2 original)
It has to be accompanied by a map of a detailed urban plan in a digital (CD) and a paper form, with routs of infrastructural networks and roads as well as guidelines and requirements for construction of infrastructure and building facilities.
2.
Revidovan glavni projekat (original)
In case a power supply is needed for a construction site, following documents are needed:
1. 01 - Libre deuda de patente
Građevinska dozvola (original)
2.
Glavni projekat (original)
3.
Odobrenje priključenja na elektro mrežu (original)
For temporary structures, following documents are needed:
1.
Odobrenje lokacije privremenog objekta (original)
2.
Glavni projekat struje (original)
In case a change in supplied power is needed, following documents are needed:
1.
Odobrenje priključenja na elektro mrežu (original)
2.
Dokaz o izmirenim obavezama (original)
3. 01 - Libre deuda de patente
List nepokretnosti (original)
4.
Glavni projekat struje (original)

Vremenski okvir

Vrijeme čekanja u redu: Min.   5mn - Max.  10mn
Zadržavanje na šalteru: Min.   5mn - Max.   10mn
Vrijeme čekanja do narednog koraka: Min.   15 dani - Max.   120 dani

Pravni osnov

1. Zakon o energetici
Zakon o energetici
Članak 176
2. Pravilnik o funkcionisanju distributivnog sistema el energije
Pravilnik o funkcionisanju distributivnog sistema el energije
Članak 40

Dodatne informacije

Note 1: Electricity Company of Montenegro has a toll-free info line 19100 that is available on weekdays from 8:00 to 20:00 o'clock. The line provides all relevant information regarding the steps in obtaining the approval for connection to electrical network.