Obtain urban development and technical requirements  (2) expand_more expand_less
Obtain the main architectural project  (2) expand_more expand_less
Obtain approval for connection to the electrical network  (2) expand_more expand_less
Obtain a measuring device  (2) expand_more expand_less
Sign a contract on connection to electrical network  (2) expand_more expand_less
Sign a contract with electricity supplier  (1) expand_more expand_less

7
Submit a request for installation of measuring device
(last modified: 03/06/2017)

Contact details

Entity in charge

Montenegrin Electricity Distribution System

Ulica Ivana Milutinovića br. 12, Podgorica 20000
Tel: +382 20 408 400
Website: www.cedis.me

Requirements

1. Request for installation of a measuring device
Request for installation of a measuring device (original)

Time frame

Waiting time in queue: Min.   10mn - Max.  15mn
Attention at counter: Min.   10mn - Max.   15mn

Legal justification

1. Law on energetics
Law on energetics
Article 123
2. The rulebook on measuring electricity
The rulebook on measuring electricity
Article 31

Additional information

Note 1: Electricity Company of Montenegro has a toll-free info line 19100 that is available on weekdays from 8:00 to 20:00 o'clock. The line provides all relevant information regarding the steps related to installation of the measuring device for connection to electrical network.