steps (11) arrow_drop_up arrow_drop_down
Obtain urban development and technical requirements  (2) expand_more expand_less
Obtain the main architectural project  (2) expand_more expand_less
Obtain approval for connection to the electrical network  (2) expand_more expand_less
Obtain a measuring device  (2) expand_more expand_less
Sign a contract on connection to electrical network  (2) expand_more expand_less
Sign a contract with electricity supplier  (1) expand_more expand_less

arrow_drop_up arrow_drop_down
chevron_right print

Preview & Print

Properties

Summary of the procedure

Institutions involved: 3 expand_more expand_less

Municipality of Podgorica (x 2)
1 2
Municipality of Podgorica
Any licensed architectural company (x 2)
3 4
Any licensed architectural company
Montenegrin Electricity Distribution System (x 5)
5 6 7 9 10
Montenegrin Electricity Distribution System

Results: 0 expand_more expand_less

-

Required Documents: expand_more expand_less

Request for urban development and technical requirement
1
Request for urban development and technical requirement
Excerpt on property ownership (x 2)
1 3
Excerpt on property ownership
Urban development request submission confirmation
2
Urban development request submission confirmation
Urban development and technical conditions (x 2)
3 5
Urban development and technical conditions
Copy of cadastral plan
3
Copy of cadastral plan
Application for connection to the electrical network
5
Application for connection to the electrical network
LLC's Tax ID number
5
LLC's Tax ID number
Revised main architectural project
5
Construction permit
5
Construction permit
Main architectural project
5
Approval for connection to the electrical network (x 2)
5 5
Approval for temporary structure's location
5
Electricity project (x 2)
5 5
Proof that all dues have been paid
5
Ownership certificate
5
Ownership certificate
Application submission confirmation
6
Request for installation of a measuring device
7
Request for installation of a measuring device
Request for a contract on connection
9
Request for a contract on connection
Request for contract with electricity supplier
11
Request for contract with electricity supplier
Contract with electricity supplier
11
Contract with electricity supplier

Cost: Free expand_more expand_less

Free of charge

Total Duration: 57 d - 190 d expand_more expand_less

  Min. Max.
Total time (sum): 57 d 190 d
of which:
Waiting time in queue (sum): 1h. 15mn 2h. 5mn
Attention at counter: 1h. 2h. 5mn
Waiting time until next step (sum): 57 d 190 d

Laws: 6 expand_more expand_less

Law on energetics Law on energetics
  articles 123, 160, 176, 178
Law on general administrative procedure Law on general administrative procedure
  Article 196
Law on Spatial Planning and Construction Law on Spatial Planning and Construction
  articles 62, 80, 93
Rulebook on technical documentation Rulebook on technical documentation
  Article 24
The rulebook on electrictricity system operations The rulebook on electrictricity system operations
  articles 40, 44
The rulebook on measuring electricity The rulebook on measuring electricity
  Article 31